Da Car, Brussels

15.12.2019
A technical tour de force! In just six weeks, we installed a huge PV carport system on the rooftop car park of the Da Car vehicle recovery firm in the heart of Brussels. The system will generate almost 600,000 kWh of green electricity per year from the sixth floor of the building.

Client

Da Car

Location

Brussels, Belgium

kWp

619

kWh

600.000

Roof surface

1,000 to 10,000 m²

Duration

Six weeks

"We are resolutely going green! We plan to install charging stations for electric cars on the roof soon. The collaboration went very smoothly."

Peter Brinckman
Project Manager at Da Car

Thank you, Da Car, for your confidence in us!